Ayer Merbau Phase 2 Marine PVD Project

Ayer Merbau Phase 2 Marine PVD Project


Project Profile

Name: Prefabricated Vertical Drains(Marine PVD)

Location: Jurong Island,Singapore

Method: Marine Prefabricated Vertical Drains(Marine PVD)

Construction duration

From: 03/2018

To:07/2018

 

Ayer Merbau Phase 2 Marine PVD Project use GPS systems to pinpoint coordinates to control barge movement Automatic recording system(s) was incorporated in the installation process of the PVDs in order to to confirm the actual depth of installation. The position of the drains, depth of penetration, joints, mandrel used for installation was recorded throughout the installation process.